- Home
- Garden notes
- Contracts, deposits and cooling-off for outdoor building work in Queensland
Garden notes ยท Contracts
Contracts, deposits and cooling-off for outdoor building work in Queensland
Ten per cent under $20,000, five per cent over, and five business days to change your mind.
Outdoor building work for a home in Queensland valued over $3,300 is done under a written contract with a cooling-off period of five business days. Before work starts on site the deposit is usually capped at 10 per cent for a contract under $20,000 and 5 per cent at $20,000 or more.
The figures are from the QBCC's Consumer Building Guide for Home Owners, in the edition effective October 2026. A contractor must hand that two-page guide over before signing any contract of $20,000 or more, and it is worth ten minutes even for a smaller job.
Deposits
| Contract | Usual maximum deposit |
|---|---|
| Price less than $20,000 | 10 per cent |
| Price $20,000 or more | 5 per cent |
| More than half the value of the work done off site | 20 per cent |
The off-site rule suits fabricated work: a steel pergola made in a workshop, a fibreglass pool shell, a kit garage.
After the deposit, the guide says progress payments should match the value of work completed on site, and gives a blunt example: nobody should be asked for half the contract price until at least half the work is done. For a garden build that means payment claims tied to things you can walk on, such as footings poured, walls up and paving laid. Delivery of materials is no measure of progress.
Cooling-off
An owner may withdraw within five business days. The clock starts the day after the owner receives a signed copy of the whole contract, plans and specifications included, and for contracts of $20,000 or more the consumer guide as well. Late paperwork extends the period. Withdrawal is by signed written notice, and the contractor can usually keep $100 plus reasonable out-of-pocket expenses incurred before the withdrawal.
Two situations remove the right: a previous contract between the same parties on substantially the same terms for the same site, and having taken formal legal advice about the contract before signing.
Variations and time
Changes are where garden budgets go. Rock under the lawn, a different paver, an extra tap: each is a variation, and the guide's advice is to agree every one in writing before the changed work begins. The contract should also state a completion date or how it is worked out. A contractor can claim more time for delays the owner causes, for approved variations, and for more rain than could reasonably have been expected, which in a Queensland summer is a clause to read closely.
After the job
The final payment is not due until the work is complete. At handover the contractor gives a defects document listing agreed items and any that are in dispute. Statutory warranties then run, generally for six years for structural defects and one year for other issues, separately from any cover under the Queensland Home Warranty Scheme. For contracts of $20,000 or more the contractor must also give a signed commencement notice within 10 business days of starting on site.
Short answers
What is the maximum deposit for a landscaping job in Queensland?
For domestic building work the QBCC states the usual maximum before work starts is 10 per cent where the contract price is less than $20,000, 5 per cent at $20,000 or more, and 20 per cent where more than half the value of the work is done off site.
Can I cancel a landscaping contract after signing?
Usually yes, within five business days of receiving the signed contract and, for contracts of $20,000 or more, the QBCC consumer guide. The contractor may keep $100 plus reasonable out-of-pocket expenses. The right does not apply after formal legal advice or under a repeat contract on the same terms.
Do these rules apply to planting and turf?
They apply to domestic building work. A contract that is only for soft landscaping is not building work, although a combined contract that includes structures over $3,300 is.
Sources
Read in November 2026. Figures and rules change, so follow the links before relying on any of them for a decision.
- QBCC, Consumer Building Guide for Home Owners (effective October 2026)
- QBCC, Cooling-off period
- QBCC, When you need a licence
Keep reading
- ContractsWhat the Queensland Home Warranty Scheme covers in the garden, and what it leaves out
- WaterWater restrictions and efficient irrigation for Queensland gardens
- PlantingWhich turf suits a subtropical garden, and which a temperate one?
This note is general information from the Great Southern Gardens editorial desk and is not legal, building or engineering advice. Spotted an error? Write to changes@greatsoutherngardens.com.